Node Router and Building 10GE uplink upgrade schedule
September 2017 - December 2017

This is a two year project to upgrade all the node routers to new Juniper routers and all the building uplinks to 10GE. Please contact Laurie Collinsworth if you have questions or concerns.


Rhodes Node: September

Building NameRouter PrepWifi vlans cut-overWired vlans cut-overBuilding uplink cut-over10G Switch Upgrade10G Switch workRouter Cleanup
301 College Ave7/16/178/11/179/28/17Replace Switch (30min)
Schuyler House7/16/178/11/179/19/17Replace Switch (30min)
Ward Lab7/16/178/11/179/19/17Replace Switch (30min)
Rhodes Hall7/16/178/11/178/11/178/15/178/15/17Upgrade module
Upson Hall7/16/178/11/179/28/17Upgrade module
Duffield Hall7/16/178/11/179/27/17Upgrade module
312 College Ave7/16/178/11/179/21/17Upgrade module
Seneca Place7/16/178/11/179/21/17n/aAlready 10G
Gates Hall7/16/178/11/179/27/17n/aAlready 10G
Phillips Hall7/16/178/11/179/27/17n/aAlready 10G
Breazzano7/16/178/11/179/26/17n/aAlready 10G
SOHO Head EndMove to IVT


Uris Node: October

Building NameRouter PrepWifi vlans cut-overWired vlans cut-overBuilding uplink cut-over10G Switch Upgrade10G Switch workRouter Cleanup
Statler HallReplace Switch (30min)
Teagle HallReplace Switch (30min)
SchoellkopfReplace Switch (30min)
MPFH (Bartels)Replace Switch (30min)
Wrestling FacilityReplace Switch (30min)
Marching BandReplace Switch (30min)
Catherwood LibraryReplace Switch (30min)
Campus StoreReplace Switch (30min)
Uris SFReplace Switch (30min)
Kite Hill Sub StationReplace Switch (30min)
Comstock HallUpgrade module
ILR ConfUpgrade module
ILR FaciltyUpgrade module
ILR Ives EastUpgrade module
Uris HallUpgrade Optic
Barton HallUpgrade Optic
Lynah RinkUpgrade Optic
BioTechn/aAlready 10G


GS Node: November

Building NameRouter PrepWifi vlans cut-overWired vlans cut-overBuilding uplink cut-over10G Switch Upgrade10G Switch workRouter Cleanup
Goldwin SmithReplace Switch (30min)
Rand HallReplace Switch (30min)
White HallReplace Switch (30min)
Sage ChapelReplace Switch (30min)
Milstein HallUpgrade module
Lincoln HallUpgrade module
Sibley HallUpgrade Optic
Tjaden HallUpgrade Optic
Johnson ArtUpgrade Optic
McGraw HallUpgrade Optic
Klarman HallUpgrade Optic
Uris LibUpgrade Optic
Olin LibUpgrade Optic
Kroch LibUpgrade Optic
Stimson HallUpgrade Optic
Day HallUpgrade Optic
Morrill HallUpgrade Optic


Humph Node: December

Building NameRouter PrepWifi vlans cut-overWired vlans cut-overBuilding uplink cut-over10G Switch Upgrade10G Switch workRouter Cleanup
Baker Inst.Replace Switch (30min)
East Hill PlazaReplace Switch (30min)
Graphic ArtsReplace Switch (30min)
HumphrysReplace Switch (30min)
Weinhold (CWReplace Switch (30min)
Heat Exchang FacilityReplace Switch (30min)
104 MapleReplace Switch (30min)
High SchoolReplace Switch (30min)
Central Heat PlantReplace Switch (30min)
Reis Tennis CenterReplace Switch (30min)
OxleyReplace Switch (30min)
110 MapleUpgrade module
CISERUpgrade module
EHOBUpgrade module
120 Maple Upgrade Optic